healthcare

Center for the Intrepid

San Antonio, Texas

Project Type: Drywall

General Contractor: Skanska

The Center was designed and built in 18 months. The fast track design build process compressed BakerTriangle’s schedule from 12 months to 8 months. Two-week look-ahead schedules were useful tools for the management team as they determined the best ways to accomplish the work. BT crews worked 6 days a week with an average crew of 35 and as many as 50 men on site at one time, self-performing more than 23,000 man hours.  The design build  process also contributed to the 296 change orders processed by BT.